4. NOTICE OF COMPLETION: 2022 CDBG STREET IMPROVEMENTS PROJECT –
F2M22-68, C2M23-7, M2M23-166
On January 23, 2023, the City Council awarded a contract for the 2022 CDBG Street
Improvements Project to Toro Enterprises Inc in the amount of $1,353,282.00. Two
change orders were issued for a total amount of $158,017.60. The change order was
issued for the installation of additional curb & gutter, concrete driveway aprons and
sidewalk repairs. The total cost of the project was $1,511,299.60. This project has been
inspected by staff and all work has been completed in accordance with the City’s
requirements and specifications. As such, it would be appropriate for the City Council to
accept this project as complete and instruct that the Notice of Completion be filed with the
County of Los Angeles Recorder’s Office.
Recommended Action: City Council accept the work of Toro Enterprises Inc. for the
2022 CDBG Street Improvements Project in the amount of $1,511,299.60 as complete;
direct the City Clerk to file a Notice of Completion with the County of Los Angeles for
recordation; instruct the Finance Director to release the 5% retention 35 days from the
date of recordation if no liens are filed; and, direct staff to undertake the steps necessary
to finalize Council’s action. (M2M23-166)