Agenda Item
· Alhambra
City Council — Item 8
Original agenda text
Item
8. NOTICE OF COMPLETION: ASSESSMENT AND REHABILITATION OF THE SEWER
MAIN AT SEWER LIFT STATION NO. 3 – F2M22-27, C2M23-15, M2M23-158
On March 27, 2023, the City Council awarded a contract to Bonadiman Water Inc. for the
Rehabilitation of the Sewer Main at Sewer Lift Station No. 3 in the amount of $289,050.00.
There were no change orders authorized to complete the project. The project has been
4
9-11-23
completed in accordance with the City requirements and specifications. As such, it would
be appropriate for the City Council to accept the project as complete and instruct the City
Clerk that the Notice of Completion be filed with the County of Los Angeles Recorder’s
Office.
Recommended Action: City Council accept the work of Bonadiman Water Inc. for
the Assessment and Rehabilitation of the Sewer Main at Sewer Lift Station No. 3 as
complete in the amount of $289,050.00; direct the City Clerk to file a Notice of Completion
with the County of Los Angeles for recordation; release the five percent retention 35 days
from the date of recordation if no liens are filed, and, direct staff to undertake the steps
necessary to finalize Council’s action. (M2M23-158)