5. NOTICE OF COMPLETION: REHABILITATION OF THE STORM DRAIN ON
MONTEZUMA AVENUE – F2M23-40, C2M23-49, M2M23-174
On June 26, 2023, the City Council awarded a contract to Sancon Technologies, Inc. for
the Rehabilitation of the Storm Drain on Montezuma Avenue in an amount of $130,045.00.
There was one change order authorized for the project, which was for additional work to
CCTV the storm drain downstream of the project area on Ramona Avenue. The change
order increased the total amount of the contract by $1,250.00, for a total of $131,295.00.
The project has been completed in accordance with the City requirements and
specifications. As such, it would be appropriate for the City Council to accept the project
as complete and instruct the City Clerk that the Notice of Completion be filed with the
County of Los Angeles Recorder’s Office.
Recommended Action: City Council accept the work of Sancon Technologies, Inc.
for the Rehabilitation of the Storm Drain on Montezuma Avenue as complete in the amount
of $131,295.00; direct the Finance Director to appropriate $1,250.00 from the Safe Clean
Water Program Fund balance and allocate the fund to account number
233.80.8882.92240; direct the City Clerk to file a Notice of Completion with the County of
Los Angeles for recordation; direct the Finance Director to release the five percent
retention 35 days from the date of recordation if no liens are filed; and, direct staff to
undertake the steps necessary to finalize Council’s action. (M2M23-174)