d. Glendale Water and Power, re: Grayson Repowering Project – Demolition and Site
Improvement Contract Contingency Amount Amendment; Balance of Site
Engineering, Procurement, and Construction (EPC) Contract Award, Professional
Services Agreement Amendment; and Wartsila North America, Inc. Engineering and
Procurement Contract Award
1. Motion authorizing an increase to the contingency amount by $10,000,000 to a new
contingency amount of $15,443,747 to the existing Contract No. 8002075 with
Silverado Contractors, Inc. (Silverado) for the Grayson Repowering Project.
2. Motion authorizing the City Manager, or his designee, to execute Amendment No. 1 to
the existing PSA, Contract No. 8002155, with ARB, Inc. (ARB), increasing the not to
exceed amount by $330,000 to a new not to exceed amount of $630,000 and to add
the following to the scope of work: 1) develop an indicative construction cost for the
Wartsila Power Island, and 2) perform the necessary engineering to support and
prepare procurement documents for long lead electrical equipment, and 3) then obtain
formal quotations.
3. Resolution authorizing the City Manager, or his designee, to execute an EPC contract
with ARB, in the not to exceed amount of $362,700,000 plus a 10% contingency of
$36,270,000 to 1) serve as the EPC for the Battery Energy Storage System (BESS)
Power Island, 2) serve as the EPC for the BOS work, 3) integration of the BESS and
Wartsila Power Islands into the Utility Operations Center, and 4) construct the Wartsila
Power Island.
4. Resolution Amending Resolution 22-189, and authorizing the City Manager, or his
designee, to execute an EP contract with Wartsila in the not to exceed amount of
$108,555,800 plus a 15% contingency of $16,283,370 to provide and deliver the
engineering design and equipment for the Wartsila Power Island.
5. Resolution of Appropriations