Victorville
City Council
Agenda Item 2
2. Award of Construction Contract to Monet Construction, Inc. and Notice of\nExemption for the New Library Renovation and Expansion, Project JM24-051\nRecommendation:\nThat the Honorable City Council:\n(1) Conduct the Public Hearing and receive testimony regarding the proposed\nproject and contract;\n(2) Close the Public Hearing;\n(3) Find the proposed project categorically exempt from the California\nEnvironmental Quality Act (“CEQA”) under CEQA Guidelines Section 15332 – In-Fill\nDevelopment Projects;\n(4) Approve a Construction Agreement in the amount not to exceed $8,621,000.00\nto Monet Construction, Inc. for the City Library Renovation and Expansion, Project\nJM24-051; and\n(5) Authorize the City Manager or his designee to execute change orders in an\namount not to exceed $862,100.00 in total, representing a 10% project contingency.\nCONSENT CALENDAR