Item
5. AWARD CONTRACT: 2023 ALLEY REHABILITATION PROJECT (AREA A / PHASE I)
– F2M23-67, N2M23-126, C2M24-2, M2M24-3
The 2023 Alley Rehabilitation Project (Area A / Phase I) consists of nine alley segments
located within the City of Alhambra’s boundaries. The alley segments selected to be
reconstructed are categorized as failed condition in the current Pavement Management
System Report. The project is located between Ethel Avenue on the West, Valley
Boulevard on the South, Marengo Avenue on the East, and Front Street on the North. City
Council authorized the circulation of a Notice Inviting Bids for this project on October 23,
2023. On November 30, 2023, the City Clerk received six bids that ranged from
$1,043,640.00 to $1,579,270.00, not including the alternate bid alley segments. Staff
reviewed the bids and found the bid received from Kalban, Inc. in the amount of
$1,043,640.00 is the lowest responsible bid. Kalban, Inc. has the necessary licenses to
complete the work and has conducted similar projects for the City of Alhambra.
4
1-8-24
Recommended Action: City Council award a contract, subject to final language
approval by the City Manager and City Attorney, to Kalban, Inc. in the amount of
$1,043,640.00 for the 2023 Alley Rehabilitation Project (Area A / Phase I); and, direct staff
to undertake the steps necessary to finalize Council’s action. (M2M24-3)