12. Change Order No. 14 to the Consulting Services Agreement (CS-0099) with CNS
Engineers, Inc. (CNS) for the Atlantic Boulevard Bridge Rehabilitation and Widening
Project
Recommendation:
A. Find that approval of the proposed change order is within the Initial Study/Mitigated
Negative Declaration prepared for this project pursuant to the provisions under the California
Environmental Quality Act (CEQA) in accordance with Section 15063 of the CEQA
Guidelines; and
B. Approve and authorize the City Administrator to execute Agreement Change Order No.
14, in substantially the same form as submitted, for the Atlantic Boulevard Bridge
Rehabilitation and Widening Project, Federal Project No. DBPL02-5139(010), Contract No.
CS-0099, amending the agreement expiration date from December 31, 2023 to December
31, 2024 and authorizing CNS to provide additional support and coordination services
required to complete the design phase of the project for the additional cost of $177,070.27
(increasing the total contract cost to $2,456,748.21), with a Change Order effective date of
December 31, 2023.