Agenda Item
· Placentia
City Council — Item c
Original agenda text
Order of Business 1
1.c. Acceptance of Construction Work and Notice of Completion
for the 2022-2023 Concrete Repair Project, City Project
No. 1302 Fiscal Impact: Expense: $ 97,500.00
Construction Contract (Grigolla) $ 9,744.00 Approved
Change Order No. 1 $ 2,665.50 Balancing Change Order
No. 2 $109,909.50 Total Construction Cost $ 1,617.29
Arborist Inspections (Dudek) $ 7,740.00 Tree Removals
(WCA) $119,266.79 Total Project Cost Budget:
$119,723.56 Total FY 22-23 CIP Budget $119,723.56
Measure U Fund (791302-6740)
Recommended Action: It is recommended that the City
Council:
1) Authorize the City Administrator to approve Balancing
Contract Change Order No. 2 with Grigolla & Sons
Construction Co. Inc, in the amount of $2,665.50;
and
2) Accept the work performed by Grigolla & Sons
Construction Co. Inc, for construction of the 2022-
2023 Concrete Repairs Project, City Project No. 1302
for a grand total amount of $109,909.50; and
3) Authorize the City Administrator to file a Notice of
Completion with the Orange County Clerk-Recorder’s
Office for the Project; and
4) Authorize the City Administrator to release retention
funds in accordance with the terms of the contract.
Staff Report
1. Contract Change Order 2
2. NOC - Grigolla & Sons Construction Co Inc.