5. 2023 GENERAL PLAN ANNUAL REPORT AND
ANNUAL MITIGATION MONITORING STATUS
REPORT FOR FEIS/EIR FOR TUSTIN LEGACY
SPECIFIC PLAN The California Government Code
requires that the Planning Commission provide an
annual progress report to the City Council on the
status of the City’s General Plan and the progress in
its implementation, including the progress in
meeting our share of regional housing needs and
efforts to remove governmental constraints to
housing development, maintenance, and
improvement. In addition, the City Council certified
the Program Final Environmental Impact
Statement/Environmental Impact Report (FEIS/EIR)
for the Disposal and Reuse of MCAS Tustin along
with its Supplemental and Addendums. The
FEIS/EIR evaluated the environmental impacts of
the reuse and disposal of MCAS-Tustin, which
included the adoption of a Mitigation Monitoring and
Reporting Program (MMRP) pursuant to CEQA
Guidelines Section 15097. The MMRP requires
annual review to ensure compliance with required
mitigations. On February 27, 2024, the Planning
Commission reviewed the General Plan Annual
Report and the Tustin Legacy Annual Mitigation
Monitoring Status Report and authorized staff to
forward the reports to the City Council. With Council
authorization, staff will forward the General Plan
Annual Report to the California Department of
Housing and Community Development (HCD) and
Office of Planning and Research (OPR) in fulfillment
of the State’s requirement, and receive and file the
Tustin Legacy Annual Mitigation Monitoring Status
Report.
Recommendation: That the City Council: Authorize
staff to forward the General Plan Annual Report to
the State OPR and HCD; and Receive and file the
Tustin Legacy Annual Mitigation Monitoring Status
Report and authorize staff to submit a subsequent
report when considerable and significant activities
occur.