10. AGREEMENT WITH BONADIMAN WATER, INC. FOR HOLLYDALE AREA WATER
MAIN REPLACEMENT
Proposed Motion:
1. Approve plans and specifications for Project 53031 Hollydale Area Water Main
Replacement Project.
2. Approve $2,281,900 Water Funds (Fund 44) budget transfer and appropriation from
Project 53250 Water Main System Replacement to Project 53031 Hollydale Area
Water Main Replacement Project.
3. Award $1,728,100 construction contract to Bonadiman Water, Inc. for Project 53031
Hollydale Area Water Main Replacement Project and authorize City Manager, or
designee, to execute and administer contract, in a form approved by the City Attorney.
4. Authorize Public Works Director, or designee, to approve future change orders for
construction and professional engineering construction support services within the
approved project budget.