10. (Continued) Hearing to Review Bidder Protests and Authorize the Award
of Construction Contract for the Barnes Park Multi-Benefit Stormwater
Capture Project (City Project No. CIP 21-198)
It is recommended that the City Council:
1. Reject the bid protest submitted by KASA Construction; and
2. If the City Council believes that Zusser Company, Inc. (âZusserâ) has
provided sufficient evidence to rebut the concerns that it is a non-
responsible bidder, the City Council should award the contract for
the Project to Zusser;
3. Alternatively, if the Council believes that Zusser has not provided
sufficient evidence to rebut concerns that it is a non-responsible
bidder, the City Council should award the contract to Nationwide
Contracting Services, Inc. Company of Huntington Beach, CA in the
amount of $17,199,044.00 (and Authorize the Mayor and City Clerk
to execute the contract with Nationwide Contracting Services, Inc);
and
4. Authorize the Director of Finance to appropriate $7,635,690.00 from
the fund and make necessary budget adjustment.
STAFF REPORT