D. Storm Water Catch Basin Award of Contract to United Storm Water Inc. for
the Storm Water Catch Basin Upgrade Project Phase II, Project No. 49018 and
Adoption of Resolution No. 2024- 08
As part of the City' s Fiscal Year 2023- 2024 Capital Improvement Program, the
City Council approved the Storm Water Catch Basin Upgrade Project Phase II.
The project consists of retrofitting sixty- six ( 66) storm water catch basins with
Automatic Retractable Screen trash capture devices to help reduce the amount of
trash entering the stormwater system and to the waterways. The project is funded by
Safe Clean Water Funds in the amount of $ 150, 000. United Storm Water Inc.
submitted the lowest responsive bid in the amount of $188, 600. Staff is requesting
to appropriate an additional $ 60, 000 in Safe Clean Water Funds to increase the total
project budget to $ 210, 000.
Recommendation: That the City Council take the following actions:
1. Approve the plans and specifications for the Storm Water Catch Basin Upgrade
Project Phase II —Project No. 49018; and
2. Authorize the City Manager to execute a contract with United Storm Water, Inc.,
for the bid amount of $ 188, 600. 00. In addition, authorize an amount of
18, 860. 00 ( 10%) as a contingency to cover the cost of unforeseen construction
expenses, for a total amount of $207, 460. 00.
3. Adopt Resolution No. 2024- 08, entitled:
A RESOLUTION OF THE CITY COUNCIL OF THE CITY OF
ROSEMEAD, CALIFORNIA, TO AMEND THE FISCAL YEAR
2023- 24 CAPITAL IMPROVEMENT PROGRAM BUDGET AND
APPROPRIATE ADDITIONAL FUNDS FOR THE STORM
4
Special & Regular Joint Meeting Agenda March 12, 2024
WATER CATCH BASIN UPGRADE PROJECT PHASE II -
PROJECT NO. 49018