Agenda Item
· Placentia
City Council — Item m
Original agenda text
Order of Business 1
1.m. Award of Construction Contract to Big Ben Engineering for
Sewer Repair Work in Old Town Placentia Fiscal Impact:
Expense: $135,000 Construction Contract $ 13,500
Contingency Amount $148,500 Total Construction Cost
Budgeted: $148,500 Total Budget $148,500 FY 23-24 CIP
Budget (799800-6750 J/L 243301-6750) Recommended
Action: It is recommended that the City Council: 1)
Approve a Public Works Agreement for Project No. 3301
with Big Ben Engineering for an amount not-to-exceed
$135,000; and 2) Authorize the City Administrator to
approve contract change orders up to 10% of the contract
not-to-exceed amount, or $13,500; and 3) Authorize the
City Administrator and/or his designee to execute all
necessary documents, in a form approved by the City
Attorney.
Staff Report
Agreement with Big Ben Engineering
Proposal