12. Approval of a Construction Contract with Gentry General Engineering Company for the Construction and Completion of Unfinished Improvements for City Project No. CIP 22-040, Calino Avenue Sewer and Storm Drain Improvements It is Staff's recommendation that the City Council: 1. Find Stance Construction Company in default of its Contract; and 2. Approve and award the construction contract to Gentry General Engineering Company of Colton, CA in the amount of $851,790.78 for the completion of unfinished improvements at Calino Avenue; and 3. Authorize the Mayor and City Clerk to execute the contract with Gentry General Engineering Company; and 4. Authorize the Director of Finance to transfer $80,000 from CIP22- 037, Acct. # 275-50-752-58100-55017 to CIP22-040, Acct #275-50- 752-58100-55021; allocate $310,617.77 to Acct 100-50-000-46950- 55021 from expected surety payment received and Acct #100-50- 752-58100-55021 for the additional expenditures and to make necessary budget adjustments.