Agenda Item
· Alhambra
City Council — Item 8
Original agenda text
Item
8. NOTICE OF COMPLETION: FRONT STREET WATER MAIN REPLACEMENT AND
ZONE CHANGE - PHASE 1 — F2M19-20, C2M23-72, M2M24-64
On August 28, 2023, the City Council awarded Contract C2M23-72 to Teichert Energy &
Utilities Group, Inc for the Front Street Water Main Replacement and Zone Change Phase 1 Project in the amount of $908,785.00. There were two authorized change orders
during the project. The change orders were to relocate a utility vault, replace irrigation
services to the median, additional paving and also included various miscellaneous items
credited to City. The change order increased the total amount of the contract by
$65,062.83, for a total project cost of $973,847.83. The project has been completed in
accordance with the City’s requirements and specifications. As such, it would be
appropriate for the City Council to accept the project as complete and instruct the City
Clerk that the Notice of Completion be filed with the County of Los Angeles Recorder’s
Office. |
Recommended Action: City Council accept the work of Teichert Energy & Utilities
Group, Inc. for the Front Street Water Main Replacement and Zone Change - Phase 1
Project as complete in the amount of $973,847.83; direct the City Clerk to file a Notice of
Completion with the County of Los Angeles for recordation; release the five percent
retention 35 days from the date of recordation if no liens are filed; and, direct staff to
undertake the steps necessary to finalize Council’s action. (M2M24-64)