3. APPROVAL OF SAN MARINO CENTER RENOVATION PROJECT NO. 20-
1000 PARTIAL RELEASE OF RETENTION IN THE AMOUNT OF $300,000
TO CABD CONSTRUCTION AND DISCUSS USE OF REMAINING
FURNITURE, FIXTURES & EQUIPMENT AND CONTINGENCY BUDGET
Recommendation: Staff recommends the City Council 1) approve Item #1 for the
installation of the lower rooftop screening, 2) approve partial release of the project’s
retention payment in the amount of $300,000 to CABD Construction, and 3) provide
direction on the remaining Items #2-4.
If the Council concurs, an appropriate motion would be:
Option 1:
“I move to approve Item #1 related to the San Marino Center Renovation (lower roof
screening), and direct staff to partially release the project’s retention payment in the
amount of $300,000 to CABD Construction.”
Option 2:
“I move to approve Item #1 and (insert any combination of items #2, #3, and #4)
AGENDA – MAY 31, 2024 Page 3 of 5
related to the San Marino Center Renovation, and direct staff to partially release the
project’s retention payment in the amount of $300,000 to CABD Construction.”