Item
Item 55: Authority to Approve Construction Change Order (CCO) 9 for K-21-1848-DBB-
3Morena Conveyance North and Extend the Construction Contract Obligations
Beyond 5 years.
Total Estimated Cost of Proposed Action and Funding Source:
This action is to execute Construction Change Order 9 to the construction contract with
OHLA USA, Inc. for a total amount of $8,445,450.00 or 8.9% increase from the original
contract award amount of $95,243,645.12 for the I-805 tunnel unforeseen soil conditions
and change to microtunneling at San Clemente Canyon and Rose Canyon tunnels.
Council District(s) Affected: 1, 6.
Proposed Actions:
Adopt the following Ordinance which was introduced on 5/14/2024, Item 53 (Council
voted 9-0):
(O-2024-109)
Ordinance authorizing the Mayor, or his Designee, to execute Change Order No. 9 to the
Construction Contract with Ohula USA, Inc. for the Morena Conveyance North in an
amount not-to-exceed $8,445,450 and adding working days that will extend the contract
for an additional twenty months for completion of construction
6 votes required pursuant to Charter Section 99.
Committee Actions Taken:
This item was heard at the Environment Committee meeting on April 11, 2024.
ACTION: Motion by Committee Member Campbell, second by Vice Chair von Wilpert,
to recommend Council approval of staff’s proposed actions.
VOTE: 3-0; LaCava-yea, von Wilpert-yea, Campbell-yea, Elo-Rivera-not present.
Engineering & Capital Projects: Akram Bassyouni, (619) 533-3616
City Attorney Contact: Elizabeth Cason