Agenda Item
· San Gabriel
City Council — Item H
Original agenda text
Order of Business 4
H. COOPERATIVE AGREEMENT WITH LOS ANGELES COUNTY FOR A TRAFFIC
SIGNAL SYNCHRONIZATION PROJECT ON MAIN STREET/LAS TUNAS
DRIVE FROM HUNTINGTON DRIVE TO GOLDEN WEST AVENUE FOR AN
ESTIMATED COST SHARE OF $361,500
On behalf of the City of San Gabriel and with City Council’s approval, the Los
Angeles County Department of Public Works (LACDPW) is set to perform a
Traffic Signal Synchronization Project (TSSP) on Main Street/Las Tunas Drive
arterial street route from Huntington Drive to Golden West Avenue, which is
jurisdictionally shared among three cities – Alhambra, San Gabriel, and Temple
City. Due to the scope and cost of the project, the County policy requires a
Cooperative Agreement to be executed for the TSSP project. The estimated
total cost of the project is $3,744,200 with San Gabriel’s estimated share cost
to be $361,500. Out of this $361,500 cost to the City, $348,851.02 will be
credited through the Federal Surface Transportation Program-Local (STP-L) to
the County in lieu of a cash payment. The remaining balance of $12,648.98 will
come from the City’s Traffic Impact Fees fund.
California Environmental Quality Act (CEQA) Determination: Not a Project as
defined in Section 15378 of the State CEQA Guidelines.
Recommended Action:
Staff recommends that the City Council adopt Resolution No. 24-36 to
appropriate $12,648.98 from the Traffic Impact Fees Fund to account 122-800-
40-97-736; authorize the City Manager to execute the Cooperative Agreement
between the City and Los Angeles County and approve the assignment of
$348,851.02 available Federal Surface Transportation Program-Local funds to
the County in lieu of a cash payment and approve a purchase order with the
County for $12,648.98 using Traffic Impact Fees funds from account 122-800-
41-97-736.