San Clemente
City Council
D. CONSIDERATION OF A RESOLUTION FINDING THAT AN EMERGENCY
EXISTS DUE TO SAND EROSION AND IMMEDIATE NEED OF SAND
PLACEMENT AT NORTH BEACH, AWARDING A CONSTRUCTION
CONTRACT TO FOR THE NORTH BEACH EMERGENCY
SAND PLACEMENT PROJECT, PROJECT NO. 14901, IN AN AMOUNT NOT
TO EXCEED $ , AUTHORIZING THE CITY MANAGER TO
EXECUTE THE CONSTRUCTION CONTRACT, AND FINDING THE PROJECT
CATEGORICALLY EXEMPT FROM THE CALIFORNIA ENVIRONMENTAL
QUALITY ACT
Staff Recommendation
Adopt Resolution No. 24-93, which would:
1. Declare that an emergency exists due to sand erosion and immediate need
of sand placement at North Beach.
2. Find the project categorically exempt from the California Environmental
Quality Act under state CEQA Guidelines Section 15269.
3. Approve transfer of funds to the project Account No. 001-636-45300-000-
14901 from the following accounts:
Transfer From Project Name Amount ($)
001-636-45300-000-19907 Army Corps Sand Project $750,000
001-636-45300-000-14809 North Beach Concession Building $300,000
001-636-45300-000-14193 North Beach Playground $150,000
001-416-45710-000-22307 Avenida Victoria Sidewalk Widening $300,000
Total: $1,500,000
4. Award the North Beach Emergency Sand Placement, Project No. 14901,
contract to .
5. Approve, and authorize the City Manager to execute,C24-38, by and
between the City of San Clemente and , for the North Beach
Emergency Sand Placement, in an amount of not to exceed
$ , in a form substantially similar to attached construction
contract (Attachment 2).
6. Approve a 10% construction contingency of $ for this project.