Item
7. CONTRACT WITH SULLY MILLER CONTRACTING CO. FOR ORANGETHORPE
AVENUE INFRASTRUCTURE IMPROVEMENTS PROJECT
Proposed Motion:
1. Approve plans and specifications for Orangethorpe Avenue Infrastructure
Improvements Project.
2. Approve the following budget transfers and appropriations in Capital Improvement
Program (CIP) Project Orangethorpe Avenue Infrastructure Project:
· $3,100,000 Road Maintenance Rehabilitation Account / Senate Bill 1 Funds (Fund
29) from CIP Project 44400 Annual Arterial Street Program to Project 44062
Orangethorpe Avenue Infrastructure Improvements Project within the Capital
Projects Fund (Fund 74)
· $50,000 Sewer Enterprise Funds (Fund 47) from CIP Project 51419 Annual Sewer
Replacement Program to CIP Project 44062 Orangethorpe Avenue Infrastructure
Improvements Project within the Sewer Enterprise Fund (Fund 47)
· $439,234 from American Rescue Plan Act (ARPA) Funds within CIP Project
53250 Water Main System Replacement and Upgrade Project (Fund 44) to Lemon
Street to CIP Project 44062 Orangethorpe Avenue Infrastructure Improvements
Project within the Water Fund (Fund 44)
· $60,000 ARPA Funds (Fund 44) from CIP Project 44054 Orangethorpe Avenue
Infrastructure Improvements - Harbor Boulevard to Lemon Street to CIP Project
44062 Orangethorpe Avenue Infrastructure Improvements Project within the Water
Fund (Fund 44).
3. Award $3,976,752 construction contract for Orangethorpe Avenue Infrastructure
Improvements Project to Sully Miller Contracting Co. and authorize City Manager, or
designee, to execute and administer the contract, in a form approved by the City
Attorney.
4. Authorize Public Works Director, or designee, to approve any future change orders for
construction and professional engineering construction support services within the
July 16, 2024 - Page 5
approved project budget.