Santa Ana
City Council
20. Construction Contract to Cabifornia, Inc. for the Santa Ana Regional Transportation
Center Fountain Renovation (Project No. 246058) (General Fund and NonGeneral
Fund)
Department(s): Public Works Agency
Recommended Action: 1. Approve an amendment to the FY 202425 Capital
Improvement Program to include $587,250 in construction funding approved in FY
202324 from the Clean California Local Grants Program through the California
Department of Transportation.
2. Approve the Project Cost Analysis for a total estimated construction delivery cost of
$587,250 which includes $435,000 for the construction contract, $65,250 for contract
administration, inspection, and testing, and a $87,000 project contingency for
unanticipated or unforeseen work.
3. Award a construction contract to Cabifornia, Inc. in accordance with the base bid in
the amount of $435,000, subject to change orders (not to exceed 25% of the base bid
amount) in accordance with the Greenbook: Standard Specifications for Public Works
Construction, for the fountain replacement of the Santa Ana Regional Transportation
Center for the term beginning upon execution of the contract and ending upon project
completion, and authorize the City Manager to execute the contract.
4. Determine that, pursuant to the California Environmental Quality Act, the