Agenda Item
· South Gate
City Council — Item 7
Original agenda text
Item
7. Agreement with Loghmani & Associates Design Group, Inc., for the construction of
Circle Park Project
The City Council will consider: (PW)
a. Approving an Agreement with Loghmani & Associates Design Group Inc. (“Agreement”), for
the construction of the Circle Park Renovation, City Project No. 609-PRK, in an amount not-to-
exceed $4,992,438, inclusive of the Base Bid and Additive Alternates A and B, with a construction
completion schedule of 165 working days; or
b. Approving an Agreement with Loghmani & Associates Design Group Inc. (“Agreement”), for
the construction of Circle Park, City Project No. 609-PRK, in an amount not to exceed
$5,167,438, inclusive of the Base Bid and Additive Alternates A, B and C, with a construction
completion schedule of 132 working days;
c. Appropriating, (a) $1,000,000 from Los Angeles County Regional Park and Open Space
District (“RPOSD”), Grant No. 10120, (b) $2,517,835 from ROPSD, Grant No. 10123, (c)
$1,500,000 from Rendon Fund, and (d) $400,000 from Rendon 2024 for a grand total
appropriation of $5,417,835, to fully fund the construction phase of the Project;
d. Authorizing the City Manager to approve change orders administratively up to a cumulative
amount of $499,239 to avoid delaying construction if change order work is needed;
e. Declaring Circle Park, City Project No. 609-PRK, to be Categorically Exempt under Title 14 of
the California Code of Regulations, Section 15301 Class 1 of the California Environmental
Quality Act ("CEQA");
f. Authorizing the City Manager to approve pre-payments of construction progress payments for
the construction contract to meet compliance with state legislation that requires payments within
30 days;
g. Authorizing the Mayor to execute the Agreement in a form acceptable to the City Attorney.
Documents:
Item 7 Report 8132024.pdf