11. AWARD OF CONTRACT FOR THE JOHN LYTTLE RESERVOIR
IMPROVEMENTS - CAPITAL IMPROVEMENT PROJECT NO. 60148
John Lyttle Reservoir is the sole water storage tank in Zone 3 of the City’s
water system, providing 150,000 gallons of emergency water storage. A
site assessment and corrosion evaluation were performed in November
2023. Details of this evaluation found moderate to severe corrosion on the
interior and exterior surfaces and recommended several safety, health,
and code improvements. Staff developed a project to recoat the interior
and exterior tank and preform related work to address recommended
improvements to extend the useful life of the existing reservoir. The City
publicly advertised and bid the project and received one bid from Unified
Field Services Corporation.
8/16/24, 4:55 PM Regular Meeting of the City Council/Special Closed Session-4:30 pm/Regular Meeting-7:00 pm
Recommendation: It is recommended that the City Council: 1. Award a
construction contract in the amount of $758,088.92 for the John Lyttle
Reservoir Improvements Project to Unified Field Services Corporation as
the lowest responsive/responsible bidder and authorize the Mayor and
City Clerk to execute the contract documents on behalf of the City; and 2.
Approve a supplemental appropriation in the amount of $338,168.92 from
the unappropriated reserves of the 2024 Water Bond Fund (Fund 307).
Fiscal Impact: Funding in the amount of $530,000 has been appropriated
in the Fiscal Year 2024-25 budget in the 2024 Water Bond Fund (Fund
307). To move forward with this agreement, staff is requesting a
supplemental appropriation of $338,168.92.