Agenda Item · Downey

City Council — Item 2

Downey August 26, 2024 City Council Item 2
Original agenda text Item
2. AWARD OF CONSTRUCTION CONTRACT FOR THE WOODRUFF AVENUE PAVEMENT REHABILITATION PROJECT, PHASE 1, BETWEEN FIRESTONE BOULEVARD AND WASHBURN ROAD, CAPITAL IMPROVEMENT PROJECT NO. 14-14A: Public Works. THAT THE CITY COUNCIL: 1) AWARD CAPITAL IMPROVEMENT PROJECT NO. 14-14A TO THE R.J. NOBLE COMPANY, THE LOWEST RESPONSIVE, RESPONSIBLE BIDDER, FOR THE TOTAL BID AMOUNT OF $1,568,424 AND WAIVE ANY AND ALL MINOR IRREGULARITIES IN THE BIDDING DOCUMENTS AS SUBMITTED BY SAID BIDDER; 2) AUTHORIZE THE CITY MANAGER, OR HIS DESIGNEE, TO EXECUTE THE CONSTRUCTION CONTRACT WITH THE R.J. NOBLE COMPANY IN THE AMOUNT OF 1,568, 424, INCLUDING ANY NON- SUBSTANTIVE EXTENSIONS, CHANGE ORDERS, PURCHASE ORDER AND AMENDMENTS UP TO THE AUTHORIZED BUDGET AMOUNT OF $2,109,751; AND, 3) APPROVE A BUDGET TRANSFER IN THE AMOUNT OF $576,979 FROM ACCOUNT NO. 56-16790 TO ACCOUNT NO. 56-16711.