Agenda Item
· Los Angeles
Board of Public Works — Item 3
Original agenda text
Item
(3)
BPW20240491
CD 14
ASPHALT PLANT NO. 1 PHASE 2 PROJECT – CALIFORNIA ENVIRONMENTAL
QUALITY ACT COMPLIANCE AND PROJECT
budget authority of $723,000, including contingency.
(W.O. E1908955, C124801)
(3)
BPW20240491
CD 14
ASPHALT PLANT NO. 1 PHASE 2 PROJECT – CALIFORNIA ENVIRONMENTAL
QUALITY ACT COMPLIANCE AND PROJECT
Recommending the Board:
In accordance with California Environmental Quality Act, review and consider the
Asphalt Plant No. 1 Phase 2 Project Final Initial Study Mitigated Negative
Declaration (FIS/MND), and adopt and forward this report and transmittal to the
City Council with the recommendations that it:
1. REVIEW and consider the FIS/MND;
2. FIND that, on the basis of the whole record, there is no substantial evidence
that the project will have a significant effect on the environment and that the
FIS/MND reflects the City of Los Angeles’ independent judgment and
analysis;
3. ADOPT the FIS/MND;
4. ADOPT the Mitigation Monitoring Program, included in Section 3 of the
FIS/MND;
5. SPECIFY that the documents constituting the record of proceedings in this
matter are in the files of the Department of Public Works, Bureau of
Engineering, Environmental Management Group, located at 1149 South
Broadway;
6. APPROVE the project as described in the FIS/MND.
ORAL REPORT(S)