Original agenda text Consent Calendar Item
CC 8. Badillo Street Water Services Replacement Project – Project No. W2501 – Award of Contract to GRBCON, Inc. for a Not-to-Exceed Amount of $379,581.20. Staff Recommendation: 1. Approve plans and specifications for the Badillo Street Water Services Replacement Project; 2. Award a contract for the Badillo Street Water Services Replacement Project to GRBCON, Inc. as the lowest responsive and responsible bidder for a not-to-exceed amount of $379,581.20 and authorize the City Manager to execute the contract; 3. Authorize a project contingency amount of $37,958.12 (approximately 10%) for any unforeseen construction expenses; and 4. Award a Professional Services Agreement to Siterep Construction Services, Inc for Inspection Services for an amount not-to-exceed $25,200 and authorize the City Manager to execute the contract.