9E. ACCEPTANCE OF THE 8930 PACIFIC AVENUE DEMOLITION AND ABATEMENT
PROJECT
The 8930 Pacific Avenue Demolition and Abatement Project consisting of the demolition
and abatement of the vacant 4-plex building located at 8930 Pacific Avenue is now
complete. The final construction cost for the project was $96,000, the contract award
amount. The City Engineer, in his judgment, certifies that the work was satisfactorily
completed as of September 11, 2024, and recommends that the City Council accept the
completed work performed on this project.
RECOMMENDED ACTION:
1. City Council declare this project categorically exempt under the California
Environmental Quality Act, Class 1, and 15301l(3); and
2. Accept the completion of improvements for the 8930 Pacific Avenue Demolition and
Abatement Project, as certified by the City Engineer, and affix the date of September
11, 2024 as the date of completion of all work on this project; and
3. Approve the final construction contract amount of $96,000 with Interior Demolition,
Inc.; and
September 24, 2024
4. Direct the City Clerk within ten (10) days from the date of acceptance to file the Notice
of Completion (Attachment) with the County Clerk-Recorder of the County of Orange;
and
5. Direct City staff, after thirty-five (35) days has elapsed from the filing of the “Notice of
Completion” with the County Clerk-Recorder, to make the retention payment to Interior
Demolition, Inc. in the amount of $4,800.