Santa Ana
City Council
22.
Construction Contract with Elecnor Belco Electric, Inc. for the Traffic Signal
Installation at Segerstrom Avenue and Spruce Street Project (Project No. 24-
6045) (General and Non-General Fund)
Department(s): Public Works Agency
Recommended Action: 1. Approve an appropriation adjustment recognizing
$132,134 in the New Transportation System Improvements Area E, Prior Year
Carry Forward revenue account (No. 03417002-50001) and appropriate the same
amount into the New Transportation System Improvements Area E, Improvements
Other Than Buildings expenditure account (No. 03417660-66220). (Requires five
affirmative votes)
2. Approve an amendment to the FY 2024-25 Capital Improvement Program to
include $132,134 in construction funding from the Transportation System
Improvement Area E account for the Traffic Signal Installation at Segerstrom
Avenue and Spruce Street Project (No. 24-6045).
3. Approve the Project Cost Analysis for a total estimated construction delivery
cost of $803,348, which includes $642,628 for the construction contract; $96,395
for contract administration, inspection, and testing; and a $64,325 project
contingency for unanticipated or unforeseen work.
4. Award a construction contract to Elecnor Belco Electric, Inc., the lowest
responsible bidder, in accordance with the base bid and bid alternates in the
amount of $642,628, subject to change orders, for construction of the Traffic
Signal Installation at Segerstrom Avenue and Spruce Street Project (No. 24-6045),
for a term beginning October 1, 2024 and ending upon project completion, and
authorize the City Manager to execute the contract.
5. Determine that, pursuant to the California Environmental Quality Act, the
recommended actions are exempt from further review. Categorical Exemption