Hawthorne

City Council

11. Progress Payment #14 and Final Acceptance in the amount of $285,610.13 due to Elecnor Belco Electric of Chino, CA for Highway Safety Improvement Project Traffic Signal Upgrade and Reconstruction 120th St Improvement Project – Prairie Ave to Felton Ave (Project # 21-06). RECOMMENDED MOTION: Staff recommends that the City Council approve this Progress Payment #14 and Final Acceptance and approve Change Order #1 to Elecnor Belco Electric of Chino, CA and release 5% retention amount 35 days after Final Approval. Award of Contract for City of Hawthorne New City Yard (Project #24-02).