Azusa

City Council

March 18, 2024 Order of Business E #12

Agenda Item 12

12. AWARD A CONTRACT FOR THE FOOTHILL BOULEVARD PAVEMENT REHABILITATION\nPROJECT – PHASE I.\nRECOMMENDED ACTION:\nAward a contract in the amount of $1,975,937.70, which includes a 10% contingency in the amount of\n$179,630 for potential change orders as needed, to CT&T Concrete Paving Inc.; and Authorize the City\nManager to execute contracts, in a form acceptable to the City Attorney, on behalf of the City.\nTotal Cost: $1,975,937.70 Is the Cost of this item budgeted? Yes\nFund/Account No: Prop C (Acct. 17-80-000-661-7120/66218A/66124A/66224B); Citywide Sidewalk\nImprovements (Acct. 10-80-000-662-7120/66222B-7120); Measure M (Fund 04); Underground Conductor\n& Development (33-40-733-670-7145; LACMTA Local-Return Funds (HIP Funds Balance); LACMTA\nLocal-Return Funds (STP-L Funds Balance)