Santa Ana
City Council
12. Construction Contract for the Construction of a Cul de Sac, Bioswale, and Crosswalk
Adjacent to Future Park on 10th Street and Flower Street (No. 221342) ( Non
General Fund) (Revive Santa Ana)
Department(s): Public Works Agency
Recommended Action: 1. Approve an amendment to the Fiscal Year 20242025
Capital Improvement Program to include an additional $1,845,898 in construction
funds for the 10th Street & Flower Street Improvements Project (No. 221342).
2. Approve the Project Cost Analysis for a total estimated construction delivery cost of
$1,845,898, which includes $1,476,719 for the construction contract; $221,507 for
contract administration, inspection, and testing; and a $147,672 project contingency
for unanticipated or unforeseen work due to the complexity and extensive scope of
this project.
3. Award a construction contract to Vido Samarzich, Inc., the lowest responsible
bidder, in accordance with the base bid in the amount of $1,476,719, subject to
change orders, for construction of the 10th Street & Flower Street Improvements
Project (No. 221342), for a term beginning October 15, 2024 and ending upon
project completion, and authorize the City Manager to execute the contract.
4. Approve adoption of a Mitigated Negative Declaration for the 10th & Flower Street
for unanticipated or unforeseen work due to the complexity and extensive scope of
this project.
3. Award a construction contract to Vido Samarzich, Inc., the lowest responsible
bidder, in accordance with the base bid in the amount of $1,476,719, subject to
change orders, for construction of the 10th Street & Flower Street Improvements
Project (No. 221342), for a term beginning October 15, 2024 and ending upon
project completion, and authorize the City Manager to execute the contract.
4. Approve adoption of a Mitigated Negative Declaration for the 10th & Flower Street
Improvements and future 10th & Flower Park, pursuant to the California Environmental
Quality Act. Mitigation measures identified in the Mitigated Negative Declaration and
Mitigation Monitoring and Reporting Program prepared for the project will be made
part of the Construction Contract.