Agenda Item
· South Gate
City Council — Item 10
Original agenda text
Item
10. Notice of Completion, and Change Order Nos. 4 & 5 to Contract No. 2023-01-CC with
California Professional Engineering, Inc. for the Tweedy Blvd. Signal Synchronization
Project
The City Council will consider: (PW)
a. Accepting completion of the construction of the Tweedy Boulevard Signal Synchronization
Project, LAMTA ID F7309, City Project No. 514-TRF (“Project”), completed by California
Professional Engineering, Inc., (“Contractor”) effective May 31, 2024;
b. Authorizing the City Manager to approve Change Order Nos. 4 and 5 to Contract No. 2023-01-
CC, which is necessary to apply costs and credits to the contract and to perform additional
construction work, in the amounts of $49,350 and $83,081, respectively; and
c. Directing the City Clerk to file the Notice of Completion with the Los Angeles County Registrar
Recorder’s Office.
Documents:
Item 10 Report 10222024.pdf