h. REJECT ALL BIDS FOR THE GUNDRY RESERVOIR ROOF REPLACEMENT
AND REHABILITATION PROJECT (PROJECT NO. 95.23001), AND RE-BID
THE PROJECT
Summary:
The Gundry Reservoir, located within Reservoir Park, is a cylindrical concrete
water storage tank with a five-million-gallon capacity, originally constructed in
1929. Over the years, the reservoir has undergone significant upgrades,
including the replacement of its wooden roof framing with a steel structure in the
1990s and the application of a watertight coating in 2006. In March 2022, an
inspection of the reservoir's interior and structural components revealed failing
structural roof members, necessitating a complete roof replacement and
recoating to maintain water quality and structural integrity.
On April 25, 2023, the City Council awarded a professional consulting services
agreement to Ardurra Group, Incorporated (Ardurra) to prepare the plans and
specifications for the Gundry Reservoir Roof Replacement and Rehabilitation
Project. Subsequently, in July 2024, Ardurra provided the final bid-ready plans
and specifications, which included the reservoir and sand basin roof
replacements, concrete repairs, exterior painting, interior recoating, and piping
rehabilitation.
On September 13, 2024, staff issued a Notice Inviting Bids for the construction
of the Gundry Reservoir Roof Replacement and Rehabilitation Project (project)
in accordance with the guidelines set forth in the Signal Hill Municipal Code
Section 1.08.010; bids were due on October 23, 2024. Upon the bid opening
date, the City received two bids; both of which exceeded the engineer’s estimate
of $2.8 million. Consequently, staff recommends the City Council reject all bids
and consider rebidding the project. If approved, the Public Works Department
would perform temporary repairs and provide necessary maintenance to ensure
the reservoir’s structural condition and water quality are maintained;
concurrently, the Public Works Department would reassess and prioritize the
project’s scope of work and pursue funding options for its construction.
Strategic Plan Goal(s):
Goal No. 1 Financial Stability: Ensure the City’s long-term financial stability
and resilience.
Goal No. 4 Infrastructure: Maintain and improve the City’s physical
infrastructure, water system, and recreational spaces.
Goal No. 5 High-Functioning Government: Strengthen internal
communications, recruitment, retention, systems, and processes to
increase the effectiveness and efficiency of City services.
Recommendation:
Authorize the Public Works Director to reject all bids received for the Gundry
Reservoir Roof Replacement and Rehabilitation Project, pursuant to Section 4.5
of the City of Signal Hill Purchasing and Contracting Guidelines and authorize
re-bidding of the project.