CC 11. Change Order No. 11 for PWCP 24-014, Lancaster Municipal Stadium Renovation
Recommendation(s):
1. Recognize revenue in the amount of $32,557.50 to General Account No. 101.40000.4514,
and appropriate an expenditure in the same amount to account CP11BS046.CONST GL Code
10149900.8000.
2. Approve Change Order No. 11 and increase the total amount of the contract with Bowe
Contractors, Inc., of Tehachapi, California, PWCP 24-014 Lancaster Municipal Stadium
Renovation, by $2,037,742.74, for a total revised contract amount of $16,158,773.74.
During construction, the Contractor encountered changed conditions. They discovered an
existing utility duct bank encased in concrete, containing 26 separate conduit runs in conflict
with the proposed renovation improvements. Contract Change Order No. 11 in the amount of