Order of Business 1
1.c
Acceptance of Construction Work and Notice of Completion for the City Hall Administrative Off
Area Improvement Project, City Project No. 5307
Fiscal Impact:
Expense: $ 130,900.00 Original Construction Contract
$ -1,022.00 Balancing Contract Change Order No. 1
$ 129,878.00 Total Construction Cost
Budgeted: $ 181,232.06 FY 2023-24 & FY 2024-25 CIP Budget
Recommended Action: It is recommended that the City Council:
1. Accept the work performed by RS Construction & Development, Inc. for
construction of the City Hall Administrative Office Area Improvement Project,
City Project No. 5307 for a total amount of $129,878.00; and
2 Authorize the Acting City Administrator to file a Notice of Completion with the
Orange County Clerk-Recorder's Office for the Project; and
3 Authorize the Acting City Administrator to release retention funds in
accordance with the terms of the contract.