Order of Business 5
b. Approve the project alignment for the joint trench utility to be
constructed west of the Bay Shore Bikeway predominantly in
Caltrans rightofway and authorize staff to negotiate with Caltrans
for approval.
2. Appropriate an additional $550,000 from CDA Loan Fund, Fund 160, to the
overall project budget to facilitate the completion or ability to complete all
easements, permits, environmental analysis, plans and specifications to
construct Phase I and position the City to be able to obtain other
funding/grants for Phase II.
3. Authorize the City Manager to approve/amend agreements with
consultants to complete the design of the project in preparation for
construction all within the project budget.