Agenda Item
· Cudahy
City Council — Item B
Original agenda text
Order of Business 12
B. Consideration to Approve Construction Contingency and Contract Change Order to the Contract
Services Agreement with Elecnor-Belco Electric, for the Salt Lake Avenue Pedestrian Safety
Improvement Project – CIP Project No. TRE-001 (page 27)
Presented by the Public Works Director
Recommendation: The City Council is requested to approve 10% Construction Contingency
in the amount of $20,018 and Contract Change Order (CCO) No. 1 in the
amount of $28,000 to the existing Contract Services Agreement in the
amount of $200,182 with Elecnor-Belco Electric, Inc., for the Salt Lake
Avenue Pedestrian Safety Improvement Project, City Project No. TRE-001,
funded by the Highway Safety Improvement Grant Program Cycle 7
(HSIP-7).