Agenda Item
· Glendale
City Council — Item c
Original agenda text
Order of Business 8
c. Public Works, re: Direction on the North Brand Boulevard Complete Streets
Demonstration Project
1. Motion adopting revised plans, directing staff to implement adjustments to the
roadway striping and installed bike lanes, executing a change order to contract
8002427 with Sterndahl Enterprises, LLC for the temporary adjustments, increasing
the contract amount by $235,120, authorizing the City Manager or his designee to
execute the contract change order, and directing staff to continue the demonstration
project for a period of six months after the adjustments (Option 1)
2. Motion adopting revised plans, directing staff to implement adjustments to the
roadway striping to convert the quick build bike lanes to two-way cycle track located
on the east side of Brand Boulevard, and return the southbound direction to two-lane
traffic configuration, executing a change order to contract 8002427 with Sterndahl
Enterprises, LLC for the adjustments, increasing the contract amount by $534,400,
authorizing the City Manager or his designee to execute the contract change order,
and directing staff to continue the demonstration project for a period of six months
after the adjustments (Option 2)
3. Motion adopting revised plans, directing staff to remove installed bike lanes and the
implemented changes, and revert the street to its original condition, executing a
change order to contract 8002427 with Sterndahl Enterprises, LLC for the reversion,
increasing the contract amount by $527,696, and authorizing the City Manager or his
designee to execute the contract change order (Option 3)
4. Resolution of appropriation to appropriate $235,120 for the North Brand Boulevard
Complete Streets Demonstration Project, to fund the implementation of the temporary
adjustments and continue the demonstration project for six months (Option 1)
5. Resolution of appropriation to appropriate $534,400 for the North Brand Boulevard
Complete Streets Demonstration Project, to fund the implementation of a two-way
cycle track alternative and continue the demonstration project for another six months
6. Resolution of appropriation to appropriate $527,696 for the North Brand Boulevard
Complete Streets Demonstration Project, to fund reverting the street to its original
alignment (Option 3)