Agenda Item
· Hermosa Beach
City Council — Item e
Original agenda text
Order of Business 17
17.e AWARD OF CONSTRUCTION CONTRACT FOR CIP 105–ANNUAL STREET
IMPROVEMENTS AND CIP 695–PARKING LOT A IMPROVEMENTS AND
APPROPRIATION OF RUBBERIZED PAVEMENT GRANT FUNDS FROM
CALRECYCLE FOR PROJECT REIMBURSEMENT - 25-PW-008
CEQA: Determine the CIP 105–Annual Street Improvements and CIP 695–Parking
Lot A Improvements project is exempt from the California Environmental Quality Act
pursuant to CEQA Guidelines Section 15301 (Existing Facilities). The proposed
work is surface improvements of an existing public roadway.
(Public Works Director Joe SanClemente)
Recommended Action:
Staff recommends City Council:
1. Award a construction contract for CIP 105–Annual Street Improvements
and CIP 695–Parking Lot A Improvements to Hardy & Harper, Inc. in the
amount of $3,200,000 (Attachment 1);
2. Authorize the Director of Public Works to establish a construction cost
contingency in the amount of $500,000 and approve contract change orders
up to the amount of the approved construction cost;
3. Adopt the attached resolution entitled "A Resolution of The City Council of
the City of Hermosa Beach Approving the Construction of CIP 105–Annual
Street Improvements and CIP 695–Parking Lot A Improvements Pursuant
to Government Code Section 830.6 and Establishing a Project Payment
Account” (Attachment 2);
4. Authorize the Mayor to execute the construction contract and the City Clerk
to attest, subject to approval by the City Attorney;
5. Accept $50,000 in grant funds from CalRecycle for CIP 105 project
reimbursement;
6. Appropriate $50,000 and add estimated revenue of $50,000 in the Grants
Fund for the Rubberized Pavement Grant Program;
7. Release $50,000 of CIP 105 project budget back to the Capital
Improvement Fund due to Cal Recycle grant funding source; and
8. Authorize the Director of Public Works to file a Notice of Completion
following final completion of the project.