Order of Business 13
13.d AWARD OF CONSTRUCTION CONTRACT FOR CIP 424 ANNUAL 1262
STORM DRAIN IMPROVEMENTS - 25-PW-002
CEQA: Determine the Annual Storm Drain Improvements project is
exempt from the California Environmental Quality Act pursuant to CEQA
Guidelines Section 15302 (Replacement or Reconstruction). The
proposed work is replacement or reconstruction of existing utility
systems and/or facilities involving negligible or no expansion of capacity.
(Public Works Director Joe SanClemente)
Recommended Action:
Staff recommends City Council:
1. Award a construction contract for CIP 424 Annual Storm Drain
Improvements to PALP, Inc. dba Excel Paving Company in the
amount of $212,260 (Attachment 1);
2. Authorize the Director of Public Works to establish a project
contingency amount of $50,000 and to approve contract
change orders up to the amount of the approved contract
contingency;
3. Adopt the attached resolution entitled “A Resolution of the City
Council of the City of Hermosa Beach Approving the
Construction of CIP 424 Annual Storm Drain Improvements
Pursuant to Government Code Section 830.6 and Establishing
a Project Payment Account” (Attachment 2);
4. Authorize the Mayor to execute the construction contract and
the City Clerk to attest, subject to approval by the City Attorney;
and
5. Authorize the Director of Public Works to file a Notice of
Completion following completion of the project.