Rosemead

City Council

D. Accept Completed Improvements and Authorize Filing of a Notice of Completion for City Project No. 24009 – Fiscal Year 2024-2025 Concrete Replacements On December 10, 2024, the City Council authorized the award of a construction contract to CT& T Concrete Paving, Inc. with a total construction budget of 390,487.08 ( including 10% construction contingency). This project included removal and replacement of existing damaged sidewalks, damaged curb and gutter, non-compliant ADA curb ramps, damaged concrete crosswalk headers, and removal and replacement of existing trees that have caused damage to concrete infrastructure within the City’ s right-of-way. Recommendation: That the City Council take the following actions: 1. Accept project completion for the Fiscal Year 2024-25 Concrete Replacement Project No. 24009 as performed by CT& T Concrete Paving, Inc. with the final contract amount of $386,125.29; and 2. Authorize the recordation of Notice of Completion with the Los Angeles County Recorder and the release of retention funds 35 days thereafter.