11.10 Acceptance of Veterans Park Stormwater Improvements (CIP
No. 3880) as Complete
RECOMMENDATION: It is staff’s recommendation that the City
Council:
1. Accept the Veterans Park City Yard Improvements Project; CIP
No. 3880 as complete, and
2. Authorize staff to file the Notice of Completion.
CONCLUSION: The City Council’s acceptance of the Project as
complete is required to allow the City Clerk to file the Notice of
Completion with the LA County Registrar-Recorder.
FISCAL IMPACT: The total Project budget included $877,551 from the
Safe, Clean Water (Measure W) Municipal Program. The Project was
completed within budget. The remaining unexpended balance will be
returned to the Measure W Fund for future stormwater-related
programs and projects.
The Veterans Park City Yard Improvements project expenditures were
as follows:
Design $ 21, 600.00
Topographic Survey & Geotechnical Infiltration $ 11,700.00
Report
Construction Management & Inspection $ 55,230.00
Project Management $ 20,580.00
Funding Administration $
7,718.00
Construction Costs $
590,430.00
Additive Bids $
100,000.00
Change Order No. 1 - 3 $ 19,322.00
Quantity Changes $ 16,549.05
Publication & Misc. Costs $ 1,225.57
Final Project Costs $
844,354.82
ATTACHMENTS: Exhibit 1 - Notice of Completion