7. APPROVE PLANS AND SPECIFICATIONS AND AUTHORIZE
ADVERTISEMENT FOR BIDS FOR THE EL CAMINO REAL WATER
MAIN RELOCATION PROJECT The plans and specifications for the El
Camino Real Water Main Relocation Project have been prepared and the
project is now ready for bid.
Recommendation: It is recommended that the City Council adopt
Resolution No. 25-27 approving plans and specifications for the El
Camino Real Water Main Relocation Project and authorize the City Clerk
to advertise to receive bids. RESOLUTION NO. 25-27 A RESOLUTION
OF THE CITY COUNCIL OF THE CITY OF TUSTIN, CALIFORNIA
APPROVING PLANS AND SPECIFICATIONS FOR THE EL CAMINO
REAL WATER MAIN RELOCATION PROJECT, CIP NO. 60178 AND
AUTHORIZING ADVERTISEMENT FOR BIDS Fiscal Impact: Utility
Agreement COT-56 between the City of Tustin and the Orange County
Transportation Authority authorizes the full reimbursement for final design
and construction costs, minus an accrued depreciation credit of $2,650. A
total of $540,000 was budgeted for the design and construction of this
project. The estimated total costs for this project are $665,326. If
necessary, additional funds will be requested after bids are received and
during consideration of the contract award.