Agenda Item
· Glendale
City Council — Item a
Original agenda text
Order of Business 8
a. Glendale Water and Power, re: Request to Increase the ARB, Inc. Balance of Site
Engineering, Procurement, and Construction Contract’s current Contingency of
$36,270,000 by $30,000,000 to a New Contingency Amount of $66,270,000 as it
Relates to the Potential Tariffs which may be Imposed on Various Equipment for the
Grayson Repowering Project
1. Motion increasing the ARB, Inc. Balance of Site Engineering, Procurement, and
Construction Contract’s, Contract No. 8002399, current Contingency of $36,270,000
by $30,000,000 to a New Contingency Amount of $66,270,000
2. Resolution of Appropriation requesting $30,000,000 for Contract No. 8002399 with
ARB, Inc