Agenda Item
· Bell Gardens
City Council — Item 13
Original agenda text
Order of Business 10
10.13
Consideration of a Resolution Approving an Agreement with
Horizons Construction Company Int’l, Inc. for the Demolition
of the Ford Park East Restroom Building
RECOMMENDATION: It is staff’s recommendation that the City
Council:
1. Approve the plans and specifications for the demolition of the
Ford Park East Restroom/Sunshine Building;
2. Adopt the attached Resolution approving an agreement with
Horizons Construction Company Int’l, Inc. for the demolition
of the Ford Park East Restroom/Sunshine Building for an
amount not-to-exceed $81,233.05; and
3. Authorize the City Manager to execute the agreement and
approve change orders that may be necessary during
construction to cover any unforeseen condition in an amount
not to exceed 10% of the agreement amount.
CONCLUSION: If the attached Resolution is adopted, staff will
process the agreement for signatures and issue a Notice to Proceed
with the Demolition Project to Horizons.
FISCAL IMPACT: The total budget for the Ford Park Playground and
Restroom Replacement Project is $1,695,394 in FY 24/25. The
agreement amount for the Demolition Project is $81, 233.05. A
contingency of ten percent (10%) (approximately $8,123.31) will be
necessary to cover any unforeseen conditions; therefore, the total
project budget for the Demolition Project is $89,356.36 consisting of
Measure A funds.
ATTACHMENTS:
Exhibit 1 - Resolution 2025-51
Exhibit 2 - Contract Agreement