Construction Contract to Vido Samarzich, Inc. for the McFadden Avenue
Transit Signal Priority Pilot Project (No. 25-6031) (Non-General Fund)
Department(s): Public Works Agency
Recommended Action: 1. Approve the Project Cost Analysis for a total
estimated construction delivery cost of $1,972,000, which includes $1,577,600
for the construction contract, $236,640 for contract administration, inspection,
and testing, and a $157,760 project contingency for unanticipated or
unforeseen work.
2. Award a construction contract to Vido Samarzich, Inc., the lowest
responsible bidder, in accordance with the base bid in the amount of
$1,577,600, subject to change orders, for construction of the McFadden
Avenue Transit Priority Pilot Project (No. 25-6031), for a term beginning July
1, 2025 and authorize the City Manager to execute the contract.
3. Determine that, pursuant to the California Environmental Quality Act, the
recommended actions are exempt from further review. Categorical Exemption
Environmental Review No. ER-2025-42 was filed for Project No. 25-6031.