14. OPTIONS FOR BARRIO TRAFFIC CALMING – 1) Adoption of a City Council resolution accepting the bids,
denying the two bid protests, awarding a contract to Palm Engineering Construction Company, Inc. for
Phase 1 of the Village and Barrio Traffic Circles Project that includes five traffic circles with sewer and
water improvements, in an amount not to exceed $5,663,385, and appropriating additional funds in
the amount of $300,000; and
2) Adoption a Carlsbad Municipal Water District Board of Directors resolution authorizing the use of
an amount not to exceed $2,516,925 from the Water System Rehabilitation and Replacement Program
funds for Phase 1 of the Village and Barrio Traffic Circles Project; or
3) Adoption of a City Council resolution directing the City Manager to return with a conceptual plan
and high-level cost estimate for traffic calming that includes one traffic circle with public art at the
intersection of Pine Avenue and Harding Street and other traffic calming measures in the Barrio area
for City council consideration at a future meeting and rejecting all bids for Phase 1 of the Village and
Barrio Traffic Circles Project; and
4) Adoption of a Carlsbad Municipal Water District Board of Directors resolution directing the
Executive Manager to return with a conceptual plan and high-level cost estimate for utilities impacted
by traffic calming that includes one traffic circle with public art at the intersection of Pine Avenue and
Harding Street and other traffic calming measures in the Barrio area for Board consideration at a future
meeting and rejecting all bids for Phase 1 of the Village and Barrio Traffic Circles Project; or
5) Adoption of a City Council resolution directing the City Manager to return with a conceptual plan
and high-level cost estimate for traffic calming that does not include traffic circles in the Barrio area
for City Council consideration at a future meeting and rejecting all bids for Phase 1 of the Village and
Barrio Traffic Circles Project; and
6) Adoption of a Carlsbad Municipal Water District Board of Directors resolution directing the
Executive Manager to return with a conceptual plan and high-level cost estimate for utilities impacted
by traffic calming that does not include traffic circles in the Barrio area for Board consideration at a
future meeting and rejecting all bids for Phase 1 of the Village and Barrio Traffic Circles Project. (Staff
contact: Tom Frank and Amanda Flesse, Public Works)
City Manager’s Recommendation: Adopt the resolutions.