$1,579,250 CONTRACT
WITH WILLIAMS PIPELINE
COURTNEY-ASH AREA WATER MAIN REPLACEMENT
approve construction and
change orders within the
CONTRACTORS, INC.
FOR
Proposed Motion:
1. Approve Courtney-Ash Area Water Main Replacement Project
specifications.
53049 plans and
2. Approve $1,830,000 Water Fund budget transfer and appropriation from Capital
Improvement Program (CIP) Project 53250 Water Main System Replacement to CIP
Project 53049 Courtney-Ash Area Water Main Replacement within the Water Fund
(Fund 44).
3. Award $1,579,250 construction contract for Courtney-Ash Area Water Main
Replacement Project to Williams Pipeline Contractors, Inc. and authorize City
Manager, or designee, to execute and administer the contract, in a form approved by
the City Attorney.
4. Authorize
Public Works Director,
or designee, to approve change
orders for
construction and professional engineering construction support services within the
approved project budget.