APPROVE CHANGE ORDERS: ROOF REPLACEMENT AT ALHAMBRA FIRE
STATION 74 – F2M24-36, C2M25-21, M2M25-129
On May 12, 2025, the City Council approved an award of contract to Superior Roofing
Systems, Inc. for the Roof Replacement project at Alhambra Fire Station 74 in an amount
not to exceed $125,256.00. Prior to the start date of the project, staff learned the roof tiles
that were identified in the scope of work developed by Weatherweld asked for a one-layer
tile instead of the two-piece clay tile currently on the building. As a result, a change order
was necessary to match the same roof tiles and preserve the same look of the roof.
Change Order No. 1 in the amount of $45,360 is the difference in price as a result of the
change in the roof material. Furthermore, during the inspection and when work started,
the contractor discovered additional plywood and insulation damage caused by termites.
Thus, Change Order Nos. 2 and 3 were submitted for the plywood replacement in the
upper deck and perimeter edge. The total amount is $51,360.00.
Recommended Action:
City Council approve Change Order Nos. 1, 2, and 3 for the
Roof Replacement Project at Alhambra Fire Station 74, increasing Contract No. C2M2521 with Superior Roofing Systems, Inc. by $96,720.00, bringing the total revised contract
value to an amount not to exceed $221,796.00 and if approved, authorize a contract
amendment in the amount of $96,720.00 for additional materials and labor, subject to
approval by the City Manager and City Attorney; and, direct staff to undertake the steps
necessary to finalize Council’s action. (M2M25-129)