City Council — Item 13
Original agenda text
Item
13.
APPROVE CHANGE ORDER: ROOF REPLACEMENT AT ALHAMBRA FIRE STATION
72 – F2M24-24, C2M25-22, M2M25-128
On May 12, 2025, the City Council approved an award of contract to Rainy Day Roofing,
Inc. for the Roof Replacement project at Alhambra Fire Station 72 in an amount not to
exceed $140,429.58. When Rainy Day Roofing, Inc. started the work, they submitted
Change Order No. 1 for all the wood and lumber that needed to be replaced upon
inspection of the wood substrate during the pre-construction walk. Change Order No. 1
was in the amount of $17,780.00 and was previously approved. Subsequently, when the
roof tiles were delivered, they were not the same as the existing roof tiles. It was
discovered that in the scope of work developed by Weatherweld, the specifications asked
for a one-layer flat tile versus the two-piece clay tile. As a result, a change order was
necessary to match the same roof tiles to preserve the same look. The total amount for
Change Order No. 2 is $94,394.21. With Change Order No. 1 and the approval of Change
Order No. 2, the original contract amount of $140,429.58 will be increased by
$112,174.21.
Recommended Action:
City Council approve Change Order No. 2 for the Roof
Replacement Project at Alhambra Fire Station 72, increasing Contract No. C2M25-22 with
Rainy Day Roofing, Inc. by $94,394.21, bringing the total revised contract value to an
amount not to exceed $252,603.79 and if approved, authorize a contract amendment in
the amount of $94,394.21 for additional materials and labor, subject to approval by the
City Manager and City Attorney; and, direct staff to undertake the steps necessary to
finalize Council’s action. (M2M25-128)